CONSTRUCTION PROGRESS
2026
Q2 2026

Second stage of column construction works (GL A/4, A/5 and A/6) 
Second stage of column construction works (GL A/4, A/5 and A/6) 
Concrete slab structural works (GL A-B/ 7-8) 
Lift core construction works (Aerial view) 
Lift core construction works (Side view) 
On-going progress of the development of the building superstructure 
Commencement of concrete casting works 
Preparation for progression to the next level, B1 
Final stage of lift core wall construction at basement level, B2 
Site progress overview - Central area consists of the completed ground-level structural elements 
Site progress overview - On-going construction activities (Excavation, structural works & material handling) at surrounding area 
Start of upper structural works above ground floor level 
Commencement of falsework & beam formwork at Level 1 
On-going progress of second cast column works at ground level 
On-going preparation for next structural elements 
Post-concreting stage of ground floor slab works 
Completion of major substructure components (Pile cap works, lift core wall starter bar installation & full concreting of the pile cap structure) 
Active reinforcement & structural works within excavation zones 
On-going slab preparation with extensive rebar installation 
On-going progress of second cast column works at ground level 
Completion of falsework & formwork installation 
Completion of reinforcement installation & formwork erection 
On-going progress of pile cap construction works 
On-going progress of secondary casting of columns 
On-going progress of secondary casting of columns 
On-going progress of secondary casting of columns
Q1 2026

Barbending works for 2nd casting 
On-going progress of hacking works on existing perimeter drain 
On-going progress of hacking works on existing perimeter drain 
Commencement of drainage works 
On-going progress of lean concrete of pile caps 
Mobilisation of tower crane 
On-going progress of lean concrete of pile caps 
Mobilisation of C60 scaffolding for ramp casting 
Completion of column base cast, Mobilisation of formworks for subsequent casting of columns 
Completion of tower crane mast installation 
Installation of second & third crane mast 
Installation of the base & first crane mast 
Installation of SW3 rebars 
Top-down system
2025